| The initial orders for the construction of the Silvretta ropeway
were placed on 25 May 1961. The building of the Silvretta lift, which
was to be of great importance for the future of both the village and
the valley, had begun.
Preliminary works and clear-felling along the route were carried
out in spring 1961 and progressed quickly. After completion of the
preliminary work, the building of a road to the mountain station
at Idalpe and access paths to the various towers and the construction
of an auxiliary ropeway (material ropeway), work started on the
superstructure of the top and base stations.
The Silvretta ropeway company was registered in the Commercial
Register on 27 October 1961. Subsequent problems arose in connection
with the Silvrettabahn during commissioning negotiations conducted
by the Federal Ministry for Transport and Electricity Supply under
State Commissioner Dr. Benesch, which, however, were soon resolved.
On 14 February 1962, the Federal Ministry for Transport and Electricity
Supply granted the Silvretta-Seilbahn AG lschgl the license to operate
the Silvretta ropeway.
The haul rope transport for the Silvrettabahn through the Montafon
over Bielerhöhe to Ischgl in the Paznaun valley took place
under most adverse conditions in August 1962.
Several advertisements announcing the imminent initial operation
of the Silvrettabahn were placed in national and international papers.
Various press articles reported on the opening: “A great dream
comes true - now the Paznaun also has its ropeway, built at a cost
of 25 million Schilling“.
On 16 March 1963, a report of damage spread like wildfire through
the village, the valley and soon the entire country:
“Haul rope ripped: Silvrettabahn cabin crashed. “
During test runs a couple of days prior to the scheduled opening,
a tow rope flashover caused the haul rope to rip, sending the descending
ropeway cabin crashing from a height of approx. 30 – 40 metres
about 100 metres before the base station. The cabin operator from
Ischgl, who was alone in the cabin, was severely injured.
After medical assistance, the man was taken to the hospital in
Innsbruck by helicopter. The ropeway was not yet authorized for
public transport. The official inspection was not scheduled to begin
until 20 March 1963. The cause of this serious accident was soon
clarified. The effective damage amounted to almost 3.5 million.
This incident together with the extra costs involved endangered
the realization of the entire project and only after tremendous
efforts could the Silvretta ropeway finally go into operation. The
transport of the 50-passenger gondolas through the Paznaun valley
took place at wintry temperatures.
After this incident, the Federal Ministry for Transport and Electricity
Supply did not grant a license for the Silvrettabahn operation until
12 December 1963. As of 15 December 1963, the Silvrettabahn went
into service and had already recorded 5,753 uphill rides and 3,864
downhill rides by the end of the year. The Idjochlift went into
service on 21 December 1963.
On 12 January 1964, the official opening of the Silvretta ropeway
and the first lift at Idalpe, the Idjoch lift, took place under
sunny winter skies. A memorable day for Ischgl and the entire Paznaun
valley.
|